EPL Skylift Takes on a Fresh Nautical Access Challenge
Lutterworth, United Kingdom, June 18, 2011 --(PR.com)-- EPL Skylift has demonstrated the effectiveness of powered access by providing equipment that allowed maintenance engineers to work on the world’s first purpose-built ship for installing offshore wind turbines.
The T58R truck-mounted platform, which has a working height of 58 metres and is capable of supporting up to 500kg, was deployed to work on the MPI Resolution, a ship designed to install wind turbines in the North Sea.
The vessel’s operator, MPI Offshore Ltd, called in EPL Skylift to use its Ruthmann-manufactured platform at the Tees Offshore Base in Middlesbrough.
MPI Resolution was raised out of the water on its six giant jacks, which are used to create a firm working platform up to 46 metres above the sea. Then, the T58R platform’s boom was sent out across the water to the 15,000 tonne ship’s hull.
The T58R truck-mounted platform was hired for three days to allow work to be carried out on thrusters at the bow of the vessel, giving the maintenance team safe access to the propellers.
The truck-mount was chosen because of its ability to easily cover the horizontal distance between the dock and the raised ship, whilst also supporting the weight of the engineering team and equipment, as well as being able to speedily set-up and depart from the busy quayside.
MPI’s Technical Superintendant, Dave Galloway, chose EPL Skylift because of its specialist equipment and proven record on reliability. He said the performance of the T58R platform was “even better than expected.”
Mr Galloway added: “The availability of a dock is not always guaranteed, so it was crucial that we worked to the time that we had. The platform presented us with a readily-available solution that gave us a convenient option to get the work done quickly and safely.
“If we had used scaffolding we’d have had to have been welding it to the vessel, whilst if we’d used a barge we’d have been reliant on the tides. The EPL Skylift option gave us a clean and reliable answer to the problem.
“The speed with which we were able to complete the job made a huge difference and allowed us to continue our operations with minimal disruption.”
For further information regarding EPL Skylift or Lavendon Access Services please contact Emily Lowth: Tel +44 (0)1455 206719 or email emily.lowth@lavendongroup.co.uk
###
The T58R truck-mounted platform, which has a working height of 58 metres and is capable of supporting up to 500kg, was deployed to work on the MPI Resolution, a ship designed to install wind turbines in the North Sea.
The vessel’s operator, MPI Offshore Ltd, called in EPL Skylift to use its Ruthmann-manufactured platform at the Tees Offshore Base in Middlesbrough.
MPI Resolution was raised out of the water on its six giant jacks, which are used to create a firm working platform up to 46 metres above the sea. Then, the T58R platform’s boom was sent out across the water to the 15,000 tonne ship’s hull.
The T58R truck-mounted platform was hired for three days to allow work to be carried out on thrusters at the bow of the vessel, giving the maintenance team safe access to the propellers.
The truck-mount was chosen because of its ability to easily cover the horizontal distance between the dock and the raised ship, whilst also supporting the weight of the engineering team and equipment, as well as being able to speedily set-up and depart from the busy quayside.
MPI’s Technical Superintendant, Dave Galloway, chose EPL Skylift because of its specialist equipment and proven record on reliability. He said the performance of the T58R platform was “even better than expected.”
Mr Galloway added: “The availability of a dock is not always guaranteed, so it was crucial that we worked to the time that we had. The platform presented us with a readily-available solution that gave us a convenient option to get the work done quickly and safely.
“If we had used scaffolding we’d have had to have been welding it to the vessel, whilst if we’d used a barge we’d have been reliant on the tides. The EPL Skylift option gave us a clean and reliable answer to the problem.
“The speed with which we were able to complete the job made a huge difference and allowed us to continue our operations with minimal disruption.”
For further information regarding EPL Skylift or Lavendon Access Services please contact Emily Lowth: Tel +44 (0)1455 206719 or email emily.lowth@lavendongroup.co.uk
###
Contact
EPL Skylift
Jamie Doran
01952 883526
Contact
Jamie Doran
01952 883526
Categories